September 2024 Construction Newsletter

SHARE

Building Momentum
Progress and Next Steps on Site

Construction Progress Update

Since our last newsletter, we’ve made significant strides on site:

  • 50% of the ground floor slab has been cast.
  • Vertical elements from the ground floor to level 1 are now underway. 
  • Drainage work across all blocks is complete.
  • Excavations have been fully completed.
  • The first pour for Block D, level 1 in the southern part of the site, has been finished.

Upcoming Works

  • Ongoing formation of the ground floor for Blocks A and C.
  • Continuation of the superstructure works for Block D.

For more detailed information, please read the full newsletter: