November 2024 Construction Newsletter
SHAREConstruction Progress Update
Since our last newsletter, we’ve made significant strides on site:
- 50% of the ground floor slab has been cast.
- Vertical elements from the ground floor to level 1 are now underway.
- Drainage work across all blocks is complete.
- Excavations have been fully completed.
- The first pour for Block D, level 1 in the southern part of the site, has been finished.
Upcoming Works
- Ongoing formation of the ground floor for Blocks A and C.
- Continuation of the superstructure works for Block D.
For more detailed information, please read the full newsletter:
Read the newsletter