August 2024 Construction Newsletter

SHARE

Since our last newsletter
we have made the following progress:

  • Completion of basement slab and vertical elements
  • Erection of formwork to GF slab
  • Two sections of the GF slab cast
  • Vertical elements from GF to L1 commenced
  • Bulk excavation nearing completion at the Northern section of the site (Blocks A & C)
  • Installation of drainage works to the Northern section of the site

Upcoming Works

  • Ongoing reinforced concrete works to GF Slab
  • Erection of formwork to L1 Block D (Southern section of the site)
  • Continuing drainage works to Northen section of site