August 2024 Construction Newsletter
SHARESince our last newsletter
we have made the following progress:
- Completion of basement slab and vertical elements
- Erection of formwork to GF slab
- Two sections of the GF slab cast
- Vertical elements from GF to L1 commenced
- Bulk excavation nearing completion at the Northern section of the site (Blocks A & C)
- Installation of drainage works to the Northern section of the site
Upcoming Works
- Ongoing reinforced concrete works to GF Slab
- Erection of formwork to L1 Block D (Southern section of the site)
- Continuing drainage works to Northen section of site